SOLUTION - PROGRAM MANAGEMENT - In Aras How can i get Gantt Chart Hourly Basis?

AbhishekSrivastava - Friday, July 29, 2016 6:25 AM:

Hello Friends,

Is there any way to view Gantt Chart on hourly basis.

 

If any solution please share.....

 

Thanks in advance

Abhishek Srivastava

 



edonahue - Monday, September 19, 2016 3:52 PM:

Hi Abhishek,

Aras doesn't currently have built-in functionality for showing a Gantt chart on an hourly basis, but there is an option to view the chart on a daily basis instead of weekly (the default selection). Once you display the Gantt chart there should be a drop-down menu that allows the choice of Day, Week, Month, Quarter, Year.



AbhishekSrivastava - Saturday, October 8, 2016 7:28 AM:

Can we Customize it, Is there any possibility?



edonahue - Monday, October 10, 2016 1:01 PM:

Hi Abhishek,

It may be possible, but I'm not positive. If you're an Aras Partner or Subscriber, I recommend contacting Aras Support for assistance with your customization. If you are not an Aras Partner or Subscriber, I recommend contacting our Community team to discuss your use case.