hi,
i created one project plan having two activity A and B, In which Activity A is Predecessor of Activity B
activity predecessor plan start plan finish duration
A 12/28/2017 12/28/2017 1
B A 12/29/2017 12/29/2017 1
if i complete Activity A two days after plan start date of A (on 12/30/2017)
then as Activity B is successor of A , how to update plan start of Activity B automatically to next day of Activity A completion Date? ( 12/31/2017)