Project Plan updation Query

hi, i created one project plan having two activity A and B, In which Activity A is Predecessor of Activity B activity      predecessor       plan start             plan finish       duration A                                      12/28/2017          12/28/2017            1 B                   A                 12/29/2017          12/29/2017            1 if i complete Activity A two days after plan start date of A (on 12/30/2017) then as Activity B is successor of A , how to update plan start of Activity B automatically to next day of Activity A completion Date? ( 12/31/2017)
Parents Reply Children
No Data